Difference between revisions of "New TLD contracting"

From ICANNWiki
Jump to navigation Jump to search
Line 24: Line 24:
  
 
==Transition to Delegation==
 
==Transition to Delegation==
 +
 +
==Delegation==
 +
 +
== Registry Onboarding ==
 
=== Sunrise Period ===
 
=== Sunrise Period ===
 
* See [[Sunrise Period]] summary
 
* See [[Sunrise Period]] summary
Line 30: Line 34:
 
*Applicant timeline examples:
 
*Applicant timeline examples:
 
=== Trademark Clearinghouse ===
 
=== Trademark Clearinghouse ===
==Delegation==
 
 
== Registry Onboarding ==
 
 
 
==References==
 
==References==
 
{{reflist}}
 
{{reflist}}
  
 
__NOTOC__
 
__NOTOC__

Revision as of 22:31, 4 December 2013

The following is an outline of the Contracting process as defined by ICANN, it is our goal to supplement this with actual contracting timelines and action items that are encountered by new TLD applicants. Information can be edited directly, or contact Andrew Merriam, andrew[at]tldesign.co

Steps & Timeline

  1. CIR (aprox. 8 days)
    1. CIR Review
  2. Sign Registry Agreement
  3. PDT (approx. 6 weeks)
  4. Transition to Delegation (approx. 2 weeks)
  5. Delegation
  6. Registry Onboarding

Contracting Information Request

Registry Agreement

Pre-Delegation Testing

The Pre-Delegation Testing (PDT) process allows ICANN to determine if registries meet specific “technical and operational requirements”[1] deemed necessary to maintain a new gTLD.

Transition to Delegation

Delegation

Registry Onboarding

Sunrise Period

  • See Sunrise Period summary
  • ICANN mandated timeline for Start Date Sunrise: 30 day notice period with a minimum of 30 days running [2]
  • ICANN mandated timeline for End Date Sunrise: no notice period, minimum of 60 days running [2]
  • Applicant timeline examples: